On 17 December 2018, Chapter 3 of the Building Industry Fairness (Security of Payment) Act 2017 commenced in Queensland, replacing the Building and Construction Industry Payments Act 2004 (Qld).
The legislation introduced significant reforms to the security of payment regime, designed to assist subcontractors in recovering amounts owed for work performed under construction contracts.
Under the current legislation, a payment claim is not required to state that it is made under the Act.
A valid payment claim must:
A payment schedule must be served within 15 business days of receiving a payment claim, unless a shorter period is specified in the contract.
If a payment schedule is not served within that time, the full amount of the claim becomes due and payable. The subcontractor may recover that amount through adjudication or court proceedings, and the contractor cannot raise a substantive defence.
There have also been changes to the adjudication process. A subcontractor now has 30 business days to lodge an adjudication application.
A contractor cannot raise new reasons in an adjudication response unless those reasons were included in the payment schedule. Failure to provide a payment schedule may also constitute an offence. The only exception is where the contractor pays the full claimed amount by the due date.
The Act also introduces a reference date following termination of a construction contract where one is not already provided. This allows a subcontractor to make a payment claim for work carried out up to the date of termination.
Payment claims made on or after 17 December 2018 are governed by the Building Industry Fairness Act, even if the construction contract was entered into before that date.
Key points for subcontractors include:
These provisions are designed to assist subcontractors to recover amounts owed in a timely and cost-effective way.
For further information, please contact Justin Mathews at justinm@qbmlaw.com.au or 0755 740111
QBM Lawyers advises contractors and subcontractors on payment claims, adjudication and construction contracts across Queensland – get clear, practical advice today.
(07) 5574 0111 | admin@qbmlaw.com.au | Mon – Fri, 08:30 – 17:00The Security of Payment regime allows contractors and subcontractors to recover progress payments under construction contracts. In Queensland, this is governed by the Building Industry Fairness (Security of Payment) Act 2017.
A payment claim is a formal request for payment under a construction contract. A payment schedule is the response, setting out the amount to be paid or the reasons for withholding payment.
If a payment schedule is not provided within the required timeframe, the claimant may have the right to recover the full claimed amount or proceed to adjudication or court action.
Yes, under current legislation, payment claims can be made even after a construction contract has been terminated, subject to the specific circumstances.
You should seek legal advice promptly. We can assist with preparing payment claims, responding to disputes, and taking steps to recover unpaid amounts efficiently.
Liability limited by a scheme approved under Professional Standards Legislation.
©2024 QBM Lawyers. All Rights Reserved
©2024 QBM Lawyers. All Rights Reserved
For over 40 years, QBM Lawyers has delivered effective legal solutions for clients across the Gold Coast.
We understand our clients’ goals, recognise the challenges they face, and provide clear, practical advice to support their commercial objectives.
Liability limited by a scheme approved under Professional Standards Legislation.
©2024 QBM Lawyers. All Rights Reserved
Liability limited by a scheme approved under Professional Standards Legislation.
©2024 QBM Lawyers. All Rights Reserved